Cubillos del Sil, ELECTRICAL GENERATION PLANT PROJECT FROM AGRICULTURAL BIOMASS AND FOREST

Buena Práctica / Bonne Pratique /

Boa Prática

NOMBRE

NOM

NAME

ELECTRICAL GENERATION PLANT PROJECT FROM AGRICULTURAL BIOMASS AND

FOREST

Localización

Localisation

Localização

El Bayo Industrial park, Cubillos del Sil is a municipality and a village of El Bierzo, in the province of León, autonomous community of Castilla y León, Spain.
Tipología – Naturaleza

Typologie – Nature

Tipologia – Natureza

Thermal power plant for heat and electricity generation.
Periodo de aplicación

Période d’application

Período de aplicação

2013-2018 Definition and realization of the project

2018-2020 Construction of the plant (ACCIONA)

€M 100

Principales objetivos

Principaux objectifs

Período de aplicação

• Boost bioenergy

• Reduce pollution

• 200 jobs for construction

• 50 direct and 300 indirect jobs

• Forest cleaning agreements and use of clearings

• Fight against fire

• Forest biomass and straw within a maximum radius of 150 km

• Attraction factor for other companies

Descripción detallada de la práctica o proyecto

Description détaillée de la pratique ou du projet

Descrição detalhada da prática ou projeto

• 100,000 m2 of plant offering 49.9 MW, for domestic and industrial consumption.

• Consumption of 280,000 tons of biomass per year, with 70% of forest fuel, obtained from the good management of poplars, pines, oaks and holm oaks. The remaining 30% will be from tree biomass, benefiting 500 farmers in the area.

• 15 years of maintenance of the construction company.

Agentes involucrados

Agents impliqués

Agentes envolvidos

  • Forestalia Renovables
  • Sociedad Pública de Infraestructuras y Medio Ambiente de Castilla y León S.A. (SOMACYL)
  • SODICAL Instituto financiero de Castilla y León
  • Banco del Consejo de Europa
Evaluación de resultados

y lecciones aprendidas

Évaluation des résultats

et les leçons apprises

Avaliação de resultados

e lições aprendidas

Fotografías

Photos

Fotos

Resultado de imagen de cubillos de sil el bayo
Solución a los retos territoriales

Solution aux défis territoriaux

Solução para os desafios territoriais

• Project works

• Specification

• Preparation and planning of the methodology

Solución a un mayor nº de retos territoriales (a completar más adelante)

Solution à un plus grand nombre de défis territoriaux (à compléter plus tard)

Solução para um maior número de desafios territoriais (a ser completado depois)

Información de contacto

Information de contact

Informação de contato

Head office: Ortega y Gasset, 20, planta 2º, 28006 Madrid

info@forestalia.es

www.forestalia.es

+34 902 50 45 81

Project funded by the European Regional Development Fund (ERDF).

BIOMASS BOILERS IN COCA

Buena Práctica / Bonne Pratique /

Boa Prática

NOMBRE

NOM

NAME

BIOMASS BOILERS IN COCA

Localización

Localisation

Localização

Coca municipality, it belongs to the province of Segovia, Castilla y León.

Tipología – Naturaleza

Typologie – Nature

Tipologia – Natureza

Forest management and supply the municipal boilers.

Periodo de aplicación

Période d’application

Período de aplicação

2000-2015

Principales objetivos

Principaux objectifs

Período de aplicação

• Cope with the rising price of fuels

• Improve in the face of the economic crisis

• Create jobs

• Improve the situation and value of wood

• Take advantage of forest waste produced in the municipality

• Reduction of CO2 emissions

Descripción detallada de la práctica o proyecto

Description détaillée de la pratique ou du projet

Descrição detalhada da prática ou projeto

In 2006 they carried out a reform in the town hall, using a biomass boiler to heat the building. The good results obtained led to the replacement of all municipal boilers.

The municipality of Coca buys the wood chips from SOMACYL and is transported from the Valladolid plant, 70 km to Coca. The price of the wood chips, at that time, was paid at € 54 / tn, placed at the silo door and with an average humidity of 30%.

Currently, it uses its own resources and has its own machinery to produce splinters.

Agentes involucrados

Agents impliqués

Agentes envolvidos

  • Coca Municipality
  • SOMACYL

Evaluación de resultados

y lecciones aprendidas

Évaluation des résultats

et les leçons apprises

Avaliação de resultados

e lições aprendidas

• Economic savings

• Reduction of CO2 emissions 28.83%

• Savings in the municipal coffers of € 57,000 per year

• Creation of direct employment to obtain biomass from forests and pruning remains

• Reduction of fire risks

• Legal instrument: assignments to SOMACYL

Fotografías

Photos

Fotos

Juan Carlos Álvarez, en el centro forestal El Sequero, en Coca./ V. M. V./

Resultado de imagen de biomasa ayuntamiento de coca

Solución a los retos territoriales

Solution aux défis territoriaux

Solução para os desafios territoriais

• Short circuit

• Production machinery

• Boiler installation

• Projects management

Solución a un mayor nº de retos territoriales (a completar más adelante)

Solution à un plus grand nombre de défis territoriaux (à compléter plus tard)

Solução para um maior número de desafios territoriais (a ser completado depois)

Información de contacto

Information de contact

Informação de contato

VILLA DE COCA MUNICIPALITY

Mayor of the municipality: Juan Carlos Álvarez

Teléfono: 921 586 011

Fax: 921 586 076

Adress: Plaza Mayor, 1 – 40480 COCA (Segovia)

Project funded by the European Regional Development Fund (ERDF).

Grouped biomass Forest management and energy use from the Cerdanya Region

Buena Práctica / Bonne Pratique /

Boa Prática

NOMBRE

NOM

NAME

Grouped biomass Forest management and energy use from the Cerdanya Region

Localización

Localisation

Localização

17 municipalities in Cerdanya, which is a territory of Catalonia located in the Pyrenean part.

Tipología – Naturaleza

Typologie – Nature

Tipologia – Natureza

Forest management, logistics center, use for boilers and commercialization.

Periodo de aplicación

Période d’application

Período de aplicação

2006-2014

Principales objetivos

Principaux objectifs

Período de aplicação

• Strengthen forest management

• Make the current operation more efficient, combining actions

• Generate more socio-economic activity for the region

• Join efforts of the institutions that will invested in the project

• Consolidation of the technical and functional structure

• Ensure the management and future improvement of the forests of Cerdanya

• Marketing of wood and / or biomass together

• Joint services hiring

Descripción detallada de la práctica o proyecto

Description détaillée de la pratique ou du projet

Descrição detalhada da prática ou projeto

A biomass availability study was carried out throughout the territory, making it for each municipality (m3). An analysis of the thermal demand of each municipality (Kwh) was carried out. Analysis of self-supply and sale of heat to other consumers. The project was analyzed from three types of scenarios and the jobs they could create were studied. Boilers installed since 2006: 30 units, with a total power of 3.7 MW.

https://es.slideshare.net/AVEBIOM/cerdanya-girona-en-la-gestin-forestal-y-uso-energtico-agrupados-de-la-biomasa

Agentes involucrados

Agents impliqués

Agentes envolvidos

Town halls, hotels, campsites, buildings of the Generalitat a Puigcerdá

Evaluación de resultados

y lecciones aprendidas

Évaluation des résultats

et les leçons apprises

Avaliação de resultados

e lições aprendidas

A first phase was carried out changing the diesel boilers of municipal buildings. They started with about 5 boilers and gradually increased until they reached about 30 boilers distributed throughout the region. Then there was a second phase in which hotels and campsites began to participate as well, reaching 44 boilers today. The boilers used are from 500 Kw with a value of € 250,000, to boilers of 70 Kw. 3,000 tons per year are what they need to supply boiler consumption. The hotels get to amortize the boilers in 3 years.

The works are carried out by municipal brigades or external companies. A chipper is rented for a short period. Each town has a warehouse of about 1000-2000 m2 to store the wood chips. The current idea would be the construction of one or two logistics centers to minimize costs. However, they are in full political debate and have trouble getting the project through.

They have no certification and for now they are not interested because it costs more.

Generally the change of boilers is not usually subsidized, but sometimes they have received aid from the Energy and Forestry Institute of Catalonia and the Gerenalitat.

On marketing, the city council directly supplies the hotels. In total 5 hotels. There is no legal instrument for the sale of the wood chips.

In the case of having a surplus, it is planned to make a sale to villages in France or Andorra.

Fotografías

Photos

Fotos

Solución a los retos territoriales

Solution aux défis territoriaux

Solução para os desafios territoriais

• Local project planning

• Economic project management

• Grouping of municipalities for the same purposes.

Solución a un mayor nº de retos territoriales (a completar más adelante)

Solution à un plus grand nombre de défis territoriaux (à compléter plus tard)

Solução para um maior número de desafios territoriais (a ser completado depois)

Información de contacto

Information de contact

Informação de contato

Francesc Cano Ibañez

Cerdanya Environment Technician

Tlf: 627 481 381

Project funded by the European Regional Development Fund (ERDF).

Serra Municipality

Buena Práctica / Bonne Pratique /

Boa Prática

NOMBRE

NOM

NAME

Serra Municipality

Localización

Localisation

Localização

Serra is a municipality of the Valencian Community, Spain. Belonging to the province of Valencia, in the region of Campo de Turia in the Natural Park of the Sierra Calderona.

Tipología – Naturaleza

Typologie – Nature

Tipologia – Natureza

Forest management, logistics center, use for boilers and commercialization.

Periodo de aplicación

Période d’application

Período de aplicação

2010-2017

Principales objetivos

Principaux objectifs

Período de aplicação

• Use of green energies

• Forest mangament

• Economic savings by the City Council

• Employment creation

Descripción detallada de la práctica o proyecto

Description détaillée de la pratique ou du projet

Descrição detalhada da prática ou projeto

The city council collects forest wastes from its area (they are an important danger to fires) and converts them into pellets in their own facilities. Part of the production is dedicated to the municipality´s own facilities, part for the neighbors and what is left over for the foreign market.

Agentes involucrados

Agents impliqués

Agentes envolvidos

  • Serra Municipality
  • LIFE PROGRAMME

Evaluación de resultados

y lecciones aprendidas

Évaluation des résultats

et les leçons apprises

Avaliação de resultados

e lições aprendidas

• Average annual savings in green waste management: € 25,000.

• Average annual energy savings: € 22,000.

• Total pellet production capacity the first year: 300 tons.

• Total pellet production capacity: 800-1,000 tons.

• Total reduction of CO2 emissions per year: 350 tons.

• Protected hectares p through forest fire prevention work: 130 ha.

• Employment created in wood pellet production plant and biomass extraction: 5 people.

 Good forest harvesting practices

 Short circuit

 Entrepreneurship giving added value to the pellet with its commercialization

 Promotion of the creation of local employment.

Currently, the Serra project wants to participate in a LIFE project in order to improve certification, increase production and marketing of the pellet.

They produce 300 tons, in a design for 800 tons. The city council uses more or less half and the rest is commercialized. To market the pellet the city council works with legal instruments. In this case it uses the payment by fees, as if they were municipal services. Later this implies a declaration of income to the city council in the documents of the Treasury.

Fotografías

Photos

Fotos


Solución a los retos territoriales

Solution aux défis territoriaux

Solução para os desafios territoriais

• Local project planning

• Economic project management

Solución a un mayor nº de retos territoriales (a completar más adelante)

Solution à un plus grand nombre de défis territoriaux (à compléter plus tard)

Solução para um maior número de desafios territoriais (a ser completado depois)

Información de contacto

Information de contact

Informação de contato

Juan José Mayans Diaz, Agronomist, Diputación de Valencia

Juanjo.mayans@dival.es

Pilar, Agronomist, Serra Municipality

Project funded by the European Regional Development Fund (ERDF).

BIOESTILHAS – BIOMASSAS E ESTILHAS LDA

GOOD PRACTICES

BIOESTILHAS – BIOMASSAS E ESTILHAS LDA

Buena Práctica / Bonne Pratique / Boa Prática

NOMBRE

NOM

NAME

BIOESTILHAS – BIOMASSAS E ESTILHAS LDA

Localización

Localisation

Localização

Trancoso – Guarda – Região Centro

Tipología – Naturaleza

Typologie – Nature

Tipologia – Natureza

ACTIVIDADES DOS SERVIÇOS RELACIONADOS COM A SILVICULTURA E EXPLORAÇÃO FLORESTAL

Periodo de aplicación

Période d’application

Período de aplicação

Desde 2011

Principales objetivos

Principaux objectifs

Principais objetivos

Impulsar a utilização de bienergia

Contratos de limpeza florestais

Luta contra incendios

Descripción detallada de la práctica o proyecto

Description détaillée de la pratique ou du projet

Descrição detalhada da prática ou projeto

Produção e Comercialização de Biomassas e Estilhas.

Exploração Florestal. Comercialização de Madeiras.

Execução de Trabalhos de Silvicultura.

Aluguer de Máquinas.

Transporte de Mercadorias em Veiculos Ligeiros.

Trabalhos de Integração Paisagistica..

Agentes involucrados

Agents impliqués

Agentes envolvidos

Municipio de Troncoso

Evaluación de resultados y lecciones aprendidas

Évaluation des résultats et les leçons apprises

Avaliação de resultados e lições aprendidas

 

Fotografías

Photos

Fotos

Solución a los retos territoriales

Solution aux défis territoriaux

Solução para os desafios territoriais

Preparação e planificação de recolha de biomassa

Implementação de uma rede de recolha e biomassa

Solución a un mayor nºde retos territoriales
(a completar más
adelante)

Solution à un plus grand nombre de défis territoriaux
(à compléter plus tard)

Solução para um maior número de desafios territoriais
(a ser completado depois)

Preparação e planificação de recolha de biomassa

Implementação de uma rede de recolha e biomassa

Información de contacto

Information de contact

Informação de contato

QUINTA NOVA, S/N

6420-593 TRANCOSO

Project funded by the European Regional Development Fund (ERDF).